Cost Sharing (Ongoing) Railway Projects

Sl. No. Name of the project *GC/ NL/ DL Length in KM Sharing pattern GoK/ MoR Estimated cost Revised Estimate GoK share MoR share Amount released 2013-14 Total Releases Balance to be released Remarks
1. 2 3 4 5 6 7 8 9 10 117 12 13
1. Ramanagara – Mysore (2007) DL 92 67 / 33 381.00 874.57(2013) 503.98 370.60 135.00 389.14 114.84 Completed
2. Hassan - Bangalore (1997) Balance Work NL 166 50 / 50 572.90 1289.92(2013) 467.21 822.71 124.00 275.17 192.04 Completed
3. Bidar - Gulbarga (2007) NL 107 50 / 50 386.00 843.00(2013) 421.50 421.50 37.00 230.17 191.5 Completed
4. Kottur - Harihar (1999) NL 65 67 / 33 326.00 425.30(2013) 283.53 141.77 - 218.33 65.2 Completed
5. Munirabad - Mehaboobanagar (Raichur)(2007) NL 170 50 / 50 350.00 1350.91(2013) 675.45 675.45 62.00 150.00 525.45 Land Acqusition Process in Progress
6. Tumkur - Rayadurga (2007-08) NL 102 50 / 50 479.59 - 239.79 239.79 20.00 60.00 179.79 Land Acqusition Process in Progress
7(a). Kadur - Chickmagalur (1996-97) NL 45 50 / 50 206.22 - 103.11 185.39 - 103.11 - Completed
7(b). Chickmagalur - Sakaleshpura NL 46 50 / 50 Land free of cost 657.80 - 328.5 328.5 15.49 LAQ - 15.49
SWR -
328.5 Land Acqusition Process in Progress
8. Kollar - Chickballapur (2006 - 07) Balance Work GC 90 50 / 50 316.08 - 158.00 158.00 158.00 Completed
9. Kudachi - Bagalkot (2010 - 11) NL 144.05 50 / 50 816.14 - 408.07 408.07 20.96 LAQ - 109.78
SWR - 30.93
377.14 Land Acqusition Process in Progress
10. Gadag – Wadi New Line (2013-14) NL 252.5 50 / 50 Land free of cost 1922.14 - 961.07 961.07 - - 961.07 Land Acqusition Process in Progress
11. Bangalore – Chamrajnagar (2007) BG 162 50 / 50 Land free of cost 1254.71 - 627.35 627.35 - - 627.35 Pending
12. Kolar Coach Factory (2011-12) 50 / 50 Land free of cost 1461.00 - 730.5 730.5 - - 730.5 MOU has been signed b/w ministry of Railways and GOK
13. Railway fiat coach factory at – Yadgiri (2013-14) Land free of cost - 46.51 - - - 46.51 Completed
14. Tumkur - Davanagere NL 200 50/50 Land free of cost 1801.01 - 900.50 900.50 - - 900.50 Land Acqusition Process in Progress
15. Shimoga - Harihara NL 76 50/50 Land free of cost 729.62 - 364.81 364.81 - - 364.81 Pending
Total 11660.21 4783.7 7219.88 7336.01 414.45 LAQ 125.27
SWR 1614.68
5605.20
Projects approved vide G.O dated 24.04.2010 not yet received detailed estimate (New Line)
Sl. No. Name of the project *GC/ NL/ DL Length in KM Sharing pattern GoK/ MoR Estimated cost
1 Whitefield - Kolar NL 52.19 50:50 land free of cost Approximately Rs.530.00 crores + cost of the land acquisition as per the new Land Acquisition Act.
2 Gadag - Haveri NL 50:50 land free of cost

Apart from this consent has been accorded to take up the following projects on cost-sharing basis.

  • Srinivaspura – Madanapalli (75 km).
  • K. R. Nagara – Kushalanagara (45 km).
  • Kadri – Puttaparthy (44 km).
  • Chikkaballapur – Puttaparthy (90 km)